- Flooring for Living Hall, Kitchen,Entertainment Rm, 3 Bedrooms, Service Yard and 2 toilets completed.
- False ceiling completed for Living Hall, Kitchen, Entertainment Rm, Master bedrm & 2 toilets.
- 1st coat of painting is completed.
- Electrical cabling 50% done. Will continue tomorrow.
- Aircon cabling fixed.
- Lighting selected and purchased.
- Furnishing selected and purchased except for Basins and Toilet Bowls (This is the most headache part for me and hubby)
Now waiting for the carpentry work to be started..hmmm such a long wait. The renovation will be delay..most probably ready by end of April.
Luzviminda have to stay in maid agency from 15th April - 31st April.