Tuesday, April 7, 2009

House Updates

  1. Flooring for Living Hall, Kitchen,Entertainment Rm, 3 Bedrooms, Service Yard and 2 toilets completed.
  2. False ceiling completed for Living Hall, Kitchen, Entertainment Rm, Master bedrm & 2 toilets.
  3. 1st coat of painting is completed.
  4. Electrical cabling 50% done. Will continue tomorrow.
  5. Aircon cabling fixed.
  6. Lighting selected and purchased.
  7. Furnishing selected and purchased except for Basins and Toilet Bowls (This is the most headache part for me and hubby)

Now waiting for the carpentry work to be started..hmmm such a long wait. The renovation will be delay..most probably ready by end of April.

Luzviminda have to stay in maid agency from 15th April - 31st April.